Tripura High Court Orders Probe Into NH Corruption Allegations
- By Thetripurapost Desk, Agartala
- Sep 09, 2026
- 222
The Tripura High Court has directed the Union government to investigate allegations of corruption and possible collusion involving contractors engaged in the construction and maintenance of NH-108B and NH-208 in Tripura.
The court's order came after repeated deterioration was reported on several stretches of the two national highways despite construction and repair efforts. The bench has asked the Centre to determine whether irregularities occurred during the selection of contractors by the National Highways and Infrastructure Development Corporation Limited (NHIDCL).
The inquiry will also examine whether NHIDCL officials and Engineering, Procurement and Construction (EPC) contractors acted in collusion and whether the alleged use of substandard materials contributed to the recurring damage.
According to the court's direction, the Union government must submit its inquiry report by December 1, 2026. If corruption or other wrongdoing is established, appropriate civil or criminal proceedings should be initiated against the officials and contractors found responsible.
Court Orders Regular Reports on Highway Repairs
The division bench comprising Chief Justice M.S. Ramachandra Rao and Justice Biswajit Palit has also directed NHIDCL to submit bi-weekly progress reports on repair and maintenance work covering four highway stretches.
The court expressed concern over the safety of people using the roads and said NHIDCL has a continuing duty to ensure that national highways remain safe and motorable, even when construction and maintenance responsibilities are assigned to EPC contractors.
The case was registered as a suo motu public interest litigation (PIL) on July 7 after media reports highlighted serious deterioration of portions of NH-108B and NH-208 and allegations concerning construction quality.
Four Tripura Highway Stretches Under Court Monitoring
The High Court's directions cover four specific sections:
-
Mohanpur-Hezamara-Subalsingh on NH-108B
-
Subalsingh-Khowai near Mahadevtila on NH-108B
-
Khowai near Mahadevtila-Srirampur on NH-208 under Kailashahar-Khowai Package-V
-
Srirampur-Manikbhandar-Bamanchara on NH-208 under Package-IV
After repairs are completed, the Border Roads Organisation (BRO) has been directed to independently audit the condition of the four stretches.
The audit report must be submitted to the High Court in a sealed cover by January 30, 2027, while NHIDCL and its contractors have been instructed to cooperate with the BRO inspection.
Road Defects Include Potholes, Cracks and Drainage Problems
A July inspection by the District Legal Services Authority, Khowai, documented extensive problems on portions of NH-208 and NH-108B.
The inspection found potholes, pavement damage, drainage deficiencies, waterlogging, road settlement and inadequate safety arrangements. The findings added to concerns already raised over the condition of the highways.
NHIDCL attributed delays and deterioration to several factors, including insufficient mobilisation of labour, machinery and construction materials by EPC contractors, heavy rainfall and recurring pavement distress.
The corporation said it had issued notices to contractors and undertaken restoration measures, including work carried out at the contractors' risk and cost.
NH-108B Project Delay Raises Court's Concern
The court also examined the progress of an NH-108B project that had originally been scheduled for completion by August 31, 2025.
According to NHIDCL's latest project information, the Agartala-Khowai NH-108B Package-II balance work remains ongoing, with the original completion schedule having been extended to December 31, 2026. NHIDCL lists the project as having around 51% physical progress.
The High Court questioned how a project that was originally expected to be completed in 2025 could remain substantially unfinished, particularly considering the reported cost involved.
Court Questions Quality and Supervision of Road Construction
The bench also considered the fact that major defects had reportedly appeared on the Subalsingh-Khowai section soon after completion.
The court said the circumstances raised concerns about the quality of construction and the level of supervision exercised by NHIDCL.
A technical inspection by the Central Road Research Institute (CRRI) was also considered during the proceedings. NHIDCL informed the court that it had been awaiting the technical assessment for guidance on restoration measures.
State Government Had Raised Concerns Over Highway Conditions
The Tripura government told the court that NH-108B and NH-208 were under NHIDCL's administrative control.
The State said its Public Works Department had informed NHIDCL about defects and requested immediate restoration. It also acknowledged concerns over the quality of execution and said NHIDCL officials had been instructed to address engineering deficiencies.
However, the State Government indicated that the pace of corrective work had remained unsatisfactory.
Read More
BCCI Partners With ChatGPT, Campa and SBI Life Till 2028
The High Court questioned why the State had not sought the transfer of administrative control back to its PWD during the relevant period to undertake maintenance work directly.
NHIDCL Has Major Highway Responsibility in Tripura
NHIDCL's own project records show that the corporation is handling multiple major highway projects across Tripura, including works on NH-108B and NH-208. Several projects remain under construction or have revised completion schedules extending into 2026 and 2027.
The court therefore emphasised that NHIDCL's responsibility extends beyond awarding contracts. It also carries an obligation to ensure that the highways under its control are maintained in a condition that does not expose road users to avoidable danger.
NHAI Says It Has No Project Role in Tripura
The National Highways Authority of India (NHAI) informed the High Court that it did not possess, execute, manage or maintain any highway project in Tripura.
The Union government had not filed a separate pleading in the case, although its Deputy Solicitor General had accepted the court's notice.
Next Hearing on September 22
The Tripura High Court has listed the matter for September 22, 2026.
The court has also directed that a copy of its order be provided to the Director General of the Border Roads Organisation.
The proceedings could have significant implications for the oversight of national highway construction in Tripura, particularly regarding contractor selection, construction quality, maintenance obligations and accountability for road safety.