Tripura Launches Clean Energy Roadmap 2035, ₹1,500 Crore Agartala Power Plan

Tripura has unveiled an ambitious clean-energy strategy aimed at accelerating renewable power generation, strengthening electricity infrastructure and creating a skilled workforce for the state's emerging green economy.

The  Tripura Clean Energy  Roadmap 2035, along with the ‘Unnayan’ green skilling programme and the Transforming Renewable Energy Acceleration in Tripura initiative, was formally launched in Agartala on Thursday in collaboration with the Asian Development Bank (ADB).

The programmes are designed to support Tripura's transition towards renewable energy while preparing its workforce for the growing demand for technical expertise in the clean-energy sector.

Tripura to Train More Than 1,000 Youth for Green Jobs

Power Minister Ratanlal Nath said renewable-energy expansion cannot depend solely on installing new infrastructure. A trained workforce will also be essential for operating, maintaining and servicing solar and other clean-energy systems.

Under the Unnayan programme, more than 1,000 people are expected to receive training.

The beneficiaries will include:

  • ITI-qualified candidates
  • Class XII pass-outs
  • Self-help group members
  • Diploma engineers
  • Technicians
  • Other prospective green-energy workers

The programme will particularly focus on modern applications of solar power and employment opportunities emerging from the state's clean-energy transition.

Ratanlal Nath Highlights Rising Demand for Skilled Workers

Nath said Tripura's rapid development over the past eight years has increased the requirement for technically qualified manpower.

Related News 

Beyond Overhead Wires: Agartala Set for Major Electricity Infrastructure Overhaul

 

He urged young people to prepare themselves for changing employment opportunities, warning that a shortage of skilled personnel could become a major challenge across different sectors in the future.

The minister also emphasised that solar expansion must be supported by a reliable maintenance ecosystem.

Tripura Supplying Power to Bangladesh, Minister Says

Speaking about the state's electricity position, Nath said Tripura is currently supplying electricity to neighbouring Bangladesh through cross-border power connectivity.

He maintained that the state is not facing a power shortage and claimed that conventional load shedding is no longer a major issue.

According to the minister, temporary interruptions occurring in certain areas should be viewed separately from scheduled or systematic load shedding.

₹1,500 Crore Underground Power Project Planned for Agartala

One of the biggest announcements at the programme was the proposed modernisation of the electricity distribution network across the Agartala Municipal Corporation (AMC) area.

The entire power infrastructure is planned to be shifted underground in phases at an estimated cost of ₹1,500 crore.

Nath said the tendering process has already been completed and the project has been awarded.

Implementation is expected to begin after the election period, with the foundation ceremony scheduled to be held in the presence of Tripura Chief Minister Prof. Dr. Manik Saha.

The underground network is expected to improve the reliability and resilience of Agartala's power distribution system while reducing the vulnerability of overhead infrastructure.

ADB Says Roadmap Will Drive Tripura's Green Energy Transition

James Kolantharaj, Principal Energy Specialist at the Asian Development Bank, said the Clean Energy Roadmap 2035 should be viewed as an actionable framework rather than merely a study or policy document.

He said the roadmap is intended to guide Tripura's renewable-energy expansion, strengthen energy security and generate new employment opportunities in the green economy.

According to Kolantharaj, ADB began preparing the roadmap in 2023 in coordination with the Tripura Government and Tripura State Electricity Corporation Limited (TSECL).

The clean-energy transition is also expected to create opportunities for youth, women, farmers, entrepreneurs and local communities.

Tripura Power Demand May Reach 800 MW by 2035

TSECL Managing Director Biswajit Basu said Tripura's current electricity demand is around 380 MW.

At present, approximately 190 MW is being exported to Bangladesh through cross-border power connections, while the state's installed solar generation capacity stands at around 60 MW.

Power demand is projected to increase substantially over the coming years.

According to Basu, Tripura's electricity requirement could reach approximately:

  • 520 MW by 2030
  • 800 MW by 2035

The projections underline the need for additional generation capacity, modern transmission and distribution infrastructure, and greater integration of renewable energy.

Rooftop Solar, Battery Storage and Green Hydrogen on Tripura's Agenda

The state is exploring several technologies to diversify its future clean-energy mix.

These include rooftop solar projects, battery energy storage systems, hydroelectric-project rehabilitation, hydrokinetic power, floating solar installations, green hydrogen and an 800 MW hydro-pumped storage project.

Such technologies could help Tripura manage rising electricity demand while increasing the contribution of renewable sources to the state's energy mix.

Agartala Power Network to Become a Smart Grid

Another major component of the modernisation programme is the conversion of Agartala's electricity distribution system into a smart grid.

The proposed infrastructure includes:

  • Underground high-voltage and low-voltage cables
  • GIS substations
  • SCADA-integrated systems
  • ADMS-based smart-grid management
  • Smart-grid control centres
  • Underground optical-fibre communication networks

The initiative is expected to provide a more technologically advanced electricity-distribution framework for the capital city.

‘Unnayan’ to Focus on Solar Energy Skills and Certification

The Unnayan green skilling programme will prepare youth and women for employment in the expanding green-energy sector.

Training will focus particularly on modern solar-energy applications and associated technical skills.

After completing the programme, successful candidates will undergo assessment and certification through an organisation recognised by the Government of India, helping improve their employability in the renewable-energy sector.

Renewable Energy Organisations Honoured

The launch event also recognised organisations that have made significant contributions to renewable-energy development.

Three organisations associated with PM-SGMBY and three organisations working under PM-KUSUM were felicitated for their performance and contribution to the clean-energy sector.

Tripura's Green Energy Push

The launch of the Clean Energy Roadmap 2035, Unnayan and the renewable-energy acceleration programme represents a broader shift in Tripura's energy strategy — combining renewable power generation, smart-grid infrastructure, underground electricity networks, energy storage and green-job creation.

With electricity demand projected to reach 800 MW by 2035, the state's clean-energy roadmap is expected to play an important role in determining how Tripura expands its power infrastructure while building a skilled workforce for the next phase of economic growth.

 

For more Tripura, Northeast, National and International news, views and analysis, follow TheTripuraPost — your trusted digital news source from Tripura.